By Katherine Salant
An architect found out the hard way that it isn't easy.
To get through the project you have to be a combination of drill
sergeant and mother hen.
Two
years ago, Rockville, MD architect Richard Donnally had reached
a point in his career where he was ready to live out his dream
- designing and building his own house. As a principle in his
own firm, Donnally, Lederer & Bujcic, he had the freedom
to rearrange his work schedule. And, after 25 years of involvement
in the building industry, he convinced his bank he had sufficient
expertise to manage the project.
Moreover,
by acting as his own contractor, he could lower the cost of his
custom-built house by about 20 percent and still include all
the features and finishes he wanted for the 4,500-square-foot
structure.
Designing
the house was "exhilarating and challenging," but once
Donnally started trying to get it built, he learned the real
reason that most people do not do this and banks discourage it.
"Building
a house is much harder than it looks. It's not rocket science,
but to do it well requires incredibly high tolerance for stress
because there will be problems every step of the way," he
said.
Just
getting to first base with a final cost figure was hard, Donnally
found.
"When
I started, I had a good idea of the going rates for labor and
materials. I thought I could just get three bids from each subcontractor
and pick the most realistic one, but I had to get 10 to 15 bids
to get one that was reasonable.
To
get a reasonable price and an honest profit margin for the concrete
work - foundation, basement, slab, sidewalks & patio - I
had to get 20 bids."
Not
only was it hard to get a reasonable price, it was hard to get
any price, Donnally said. "I would give a sub specs and
drawings and then the guy never called back. The truth is, though
your project is everything to you, you are a small deal to suppliers
and trades people. They give preference to the guy building a
lot of houses because he can give them steady work.
"The
thing that really drives you crazy in getting bids is that there
are more than 30 tradesmen on your job. The granite counter top
guy, the cultured marble counter top guy, the gutter guy, the
roof guy, each one only does that one specific job. You don't
realize before you start the number of people you must get bids
from."
Include
Everything in the Bid
As
Donnally,'s house went up, he learned another critical fact about
bidding. "When you ask for a bid, you can't assume that
your bidder will include everything that is required but not
specified. For example, I assumed that the guys who hang the
interior doors would include the hardware (door handles and latch
plates) in their price. They didn't. I had to go out and get
these and pay an extra labor charge to get them included. An
experienced general contractor would have said, "When bidding
interior doors, include hardware."
"Some
of the confusion about what was included [in the bid] and what
wasn't was caused by the lack of detail in my own drawings. In
the commercial work that I usually design, everything is detailed
and specified, down to the length, finish and spacing of each
screw. We have at least 50 sheets of details and a very thick
book of specifications. If you hired an architect to design a
house with 50 sheets of details, the fee could be as much as
$100,000. You won't get that level of detail in residential projects,
so there are a lot of openings for mistakes and use of inferior
materials."
When
Donnally finally assembled all the bids and started to build
his house, the work proceeded in fits and starts.
"The
subs would meet my price but not show up. Or they would show
up for a few days and disappear to do other jobs. I discovered
that a mark of a really good sub is not just the quality of his
work. He is also really organized and doesn't commit to more
than he can handle.
"When
one sub didn't show up, I had to cancel and reschedule the others
who were to come next. They would go to other jobs and it was
hard to get them rescheduled back to me."
One
solution to the no-shows that Donnally tried was getting the
subs who did reliably show up to take on more work. "This
was a mistake. I learned the hard way that when a sub is recommended
for one thing, don't ask him to do something he doesn't do 100
percent of the time. My framing carpenter said he could do finish
carpentry, but he was lousy."
All
the no-shows and rescheduling strung the job out months longer
than Donnally had anticipated.
"My
original estimate for building my house was eight months. Then
I thought 10 months was more realistic, but 12 months was what
it took."
Keeping
Control of Quality
Quality
control was another issue for this rookie builder.
"Some
mistakes were easy to spot. My wife, for example picked up that
the sink base was not centered with the window above it. But
the average person couldn't tell if you have a proper footing
or enough nails in the framing. You can't depend on a municipal
building inspector to make sure that these are done correctly.
Some are more careful than others, but they spend only a few
minutes at the job site. For the framing and foundations work
- critical for the structural integrity of your house - I did
a lot of checking and I got a lot of references.
"If
I spotted a mistake when work was just starting for the day and
the subs hadn't done much, it was easy to get them to redo things
if there was a disagreement. But if a sub installed 20 of something
the wrong way, it was hard to get him to change it. Often the
problem was a gray area that was not well detailed on the plan.
I thought it didn't look right, but to do it my way, the sub
often wanted extra money."
Staying
on top of everything was "unbelievably time consuming,"
Donnally discovered. "To keep things going, I had to be
there a lot more than I had thought. At the beginning, I was
at the job site only once a week, then twice a week, but the
last month, when we were racing to finish, I was there every
day for two to four hours. It was a good thing I am a partner
in my firm or I would have been fired. I managed to move my work
around and I worked a lot of late nights."
Developing
the right management style was another challenge, Donnally found.
"You
can be tough and mean and get the work done. But if you're too
mean, the subs will walk off. A colleague came to look at the
job and spoke sharply to one person and he didn't come back for
three days. You have to have a sense of humor and be encouraging.
You have to be stern. Subs can be like teenagers and never clean
up after themselves. I had to get a cleaning service in halfway
through construction because there was so much trash and sawdust
and debris.
"In
short, to run such a project well, you have to be a mix of a
drill sergeant and a mother hen. And you have to have an incredibly
high tolerance for stress. Problems will occur and you must know
how to fix them. As a friend said, 'Construction is knowing how
to fix a mistake and make it look good."
Now
that he's finally finished and moved into his new house, would
he do it again?
"By
doing it this way I saved about $100,000 and got the house I
wanted. But if I'd had a $100,000 more, I would have hired a
general contractor in a second."
Katherine
Salant of Ann Arbor, Michigan writes consumer advice columns
for buyers of new houses. She can be reached by mail at Inman
News Features, 1250 45th St., Suite 360, Emeryville, California
94608 or through e-mail:salantques@aol.com.